HR ManagementRecruitment (ATS)Payroll & WPSTime & AttendanceAccounting & E-InvoicingCRM & Sales PipelineSales Orders & FulfilmentInventory, Purchasing & WarehousingProcurement & TendersConstruction & ContractingContracts & E-SignatureProducts & Online StorePoint of SaleRentalsSubscriptions & LicensingHelpdesk & TicketingSocial Media SuiteInfluencer Marketing & Campaign ROIProject ManagementActivities WorkspaceDocument ManagementPDF Tools & E-SignatureCorrespondence RegisterTeam Chat & CallsMeetings & VideoLearning & Certification (LMS)Asset ManagementFleet ManagementRecognition & GamificationContacts & PartnersNotification CentreReports & DashboardsInsights — Business Intelligence & AppsAI CopilotAI Agents & AutomationAI Diagram StudioWebsite BuilderISO Compliance Suite (Imtithal)App MarketplaceCustomer & Partner PortalSecurity, Access & Compliance

A subcontractor is certified, billed and paid

Who is involved

RoleWhat they do
Quantity surveyorPrepares and certifies the certificate.
Construction managerApproves and issues the subcontract.
AccountantRecords the bill and the payment.

Step by step

  1. Quantity surveyor

    Makes a draft subcontract from a work package, gives every line its cost code and submits it.

    What they see:The subcontract waits for approval.

  2. Construction manager

    Approves and issues the subcontract and records the signed copy.

    What they see:The subcontract is running and its lines are committed cost on the budget.

  3. Quantity surveyor

    Starts a certificate for the period, types the work done, adds any contra charges and submits it.

    What they see:The certificate shows the net after retention, advance recovery and contra charges.

  4. Quantity surveyor

    Certifies it. A person who did not submit it must do this when the separation rule is on.

    What they see:The certificate is certified and waits for its bill.

  5. Accountant

    Records the subcontractor's bill, then the payment.

    What they see:The work done becomes job cost and the commitment falls by the same amount.

Who is told what

The accountant is told when a certificate is certified. Retention held back from the subcontractor stays payable until it is released.